NGE reinforces the safety of the Orédon dam in the face of extreme flooding for SHEM

qrcode
Construction site
By Bat info source: NGE via Bureau Eilo

NGE will build the new spillway for the Orédon dam (Hautes-Pyrénées) on behalf of SHEM, an ENGIE subsidiary. This project, which began in early April 2026 and is scheduled to last three years, will increase the maximum capacity of the current spillway from 50 m³/s to 213 m³/s in order to cope with a 10,000-year flood event.