Some 250 companies and hundreds of craftsmen, architects and professionals worked on this extraordinary project to allow the reopening of the masterpiece of Gothic art, still scheduled for December 8, affirms AFP Mr. Jost, who has headed the public establishment responsible for this restoration since the death of General Jean-Louis Georgelin last summer.
On April 15, 2019, a gigantic fire ravaged the cathedral, a symbol of Christianity listed as a UNESCO world heritage site which welcomed 12 million visitors each year. It caused the collapse of its spire and the partial collapse of its roof, ravaged by the flames.
Millions of people were stunned by the images broadcast live.
Clearing and securing
“We all experienced the shock of the cathedral after the fire, with these visions of desolation: the gaping breaches in the vaults, the rubble which littered the ground. We used robots because we could not penetrate under the vaults. The security phase lasted more than two years,” recalls Mr. Jost, who was initially General Georgelin’s right-hand man.
Tons of rubble (charred wood, collapsed stones, etc.) had to be cleared. A construction site interrupted for several weeks due to Covid.
Securing continued with the bending of the flying buttresses which support the vaults, which in turn threatened to collapse, as well as the decontamination of 450 tonnes of lead partially vaporized in the atmosphere.
An exterior scaffolding of 40.000 twisted and charred tubes, which surrounded the spire before the fire (of which 16 statues had been dismantled for restoration), was dismantled.
This “major step” under high security was completed in the summer of 2021, at a cost of 150 million euros.
Reconstruction
Reconstruction began in the fall of 2021 on the cathedral construction site (where interior and exterior scaffolding was installed) and in numerous art workshops (carpenters, master glassmakers, stonemasons, etc.).
Among the technical challenges, Mr. Jost cites the frames of the nave, the choir and the spire, which could be reconstructed identically in solid oak, with more than a thousand bicentennial trees specially selected from the forests. French.
They were all completed in March, the spire, identical to that of the 19th century architect Viollet-le-Duc, having also recovered part of its cover and its lead ornaments, as well as its cross and its rooster.
Among the “very great moments”, Mr. Jost cites “April 2023, when the masons-stonecutters closed the large breach in the vault of the nave” and when “the spire reappeared in the eyes of all” in February 2024 .
The overall budget for this reconstruction phase should remain "below" the 550 million euros initially estimated, Mr. Jost anticipates.
846 million euros in donations were collected around the world, of which around 150 must be used to restore exterior parts of the cathedral which were very eroded and affected by various stone pathologies before the fire.
Interior
Inside, Notre-Dame has regained a luminosity unknown in living memory: the cleaning of the walls, vaults and decorations is almost complete.
It reveals the blondness of the Ile-de-France stone and the painted decorations which were buried under layers of dirt. The replacement of the black and white checkerboard floors continues, as well as the completely redesigned installation of technical and electrical devices and a new fire-fighting system, according to Mr. Jost.
The diocese has chosen to purify the central axis of the cathedral and provide it with new massive and sober liturgical furniture in brown bronze, as well as 1.500 chairs with an openwork design in solid oak, which will be installed in the fall. .
The stained glass windows (of which only three large roses are medieval) were not damaged by the fire but they have all been cleaned. Six contemporary stained glass windows should integrate certain chapels on the Seine side, but not before 2026, according to the wishes of the President of the Republic.
The great organ (the largest in France) was spared by the fire but covered in lead dust. After cleaning, its 8.000 pipes were reassembled one by one. Its harmonization should last six months to restore its “voice” to Notre-Dame.
Next steps
By summer, the roofs of the nave, chancel and spire, restoration of the floors, as well as work on interior art furniture, must be completed.
From the fall, the square and the accesses will be cleared and redeveloped in conjunction with the City of Paris, responsible for restructuring the surrounding area, which must be greened by 2028.